Installations

Northrup Elementary School (Alhambra USD)

This installation replaced the majority of this site’s existing portable classrooms. The scope included supply and installation of one DSA Pre-Approved, two story, 8 classroom building (totaling 15,000 square feet) and associated sitework.  The schedule duration for in-plant prefabrication and installation and sitework construction was five months with completion occurring in September 2009. This project was installed concurrently with the Garfield Elementary School Project.