Garfield Elementary School (Alhambra USD)

This installation replaced all of this site’s existing portable classrooms. The scope included supply and installation of one DSA PC Pre-Approved, Two Story, 10 classroom Plantcrafted Buildings® (totaling 17,500 square feet) and associated sitework.  The schedule duration for in-plant prefabrication and installation and sitework construction was six months with completion occurring in October 2009.